1,Description:
XXXXX O01_BBU01 NR Cell Unavailable  ,NR DU Cell TRP Unavailable,  AAU2 link  faulty.
Red   light on board UBBPg2a( interface01, Slo5 of BBU)
2,Alarm PIC:
As showedn in Sheet "PIC"
3, Prior  Analysis:
3.1
Xn interface Faulty
X2 interface Faulty
This arlarm normally dut to  configuration of neibour cell
it should be debugged on the background,not SE' duty.
3.2
DU cell TRP unavaliable
This arlarm normally dut to software  version update.
it should be debugged on the background,not SE' duty.
3.3
RU Unit CPRI interface Error
Red   light on board UBBPg2a( interface01, Slo5 of BBU)
it is SE' duty to test.
4,Preparation:
Tools:Multimeter
Optical power meter if can
Laptop
Cellphone with camera
Safety suits and protective tools
Tools box inludeing wrenchs,  screwdrivers,and so on.
Spare:
SFP if can
CPRI if can
UBBPg2a if can
Accessories including Waterproof  mastic,Waterproof tape,Electrostatic discharge tape,copper lugs and so on.
5, Switch  Test
  
5.1
Points for attention
The principle of switching test is  due to elimination method
Each time only switch one  component.By test, we can tell if the component ok.
And in order to  prove that action is always right, we  should take a picture after every check.
Because we have identified that it  is link or AAU or interface problem, so we just check link light in switch  test.
For   cell working well or not, we don't care it in testing.
5.2
The objects will be tested
Power of AAU--AAU is a precision  device, so it is very sensitive to voltage
SFP on board UBBPg2a( interface01,  Slo5 of BBU)
SFP of AAU2
CPRI of AAU link
the interface 01 of board UBBPg2a(  Slo5 of BBU)
AAU5645
Confustion 1:
AAU on site, but  in my  list, there should be  RRU.
5.3
The processIn test, pls note  SN  codes of all tested emothion.
5.3.1Take pic
take a photo on BBU panel
Take a photo on board UBBPg2a(  interface01, Slo5 of BBU)
Take a photo on board UBBPg2a(  interface01, Slo4 of BBU)
take a photo on AAU2 type label
take a photo on AAU2 light
5.3.2Power Checking
Firstly ,checking the power of  output to AAU2 from DCDP in cabnet.Take a PIC pls.
Secondly checking the power of input  to AAU2 on the tower or manpole.Take a PIC of AAU2 lights pls.
Remark: Loose joints can easily cause problems or burn out of the equipmen
5.3.3SFP of BBU checking
In switch test, we want to find the  broken part.
So please just change the part to be tested  to another good cell link.
Because there may be damage to  multiple parts, every part needs to be switch tested.
Certenly, when all parts have been  tested, we can move good part to broken AAU2 link for confirmation.
Pls apply permission from NOC,  firstly.
5.3.2.1Move SFP on board UBBPg2a( interface01, Slo5 of BBU) to other good cell  link.
if the good cell link still up, the tested SFP is good.
Otherwise, the tested SFP is fault.
pls take a PIC for this to show light status.
Return to the replaced unit to restore the original good link to normal
Make sure the link light back green.
5.3.2.2If there  is  SFP on board UBBPg2a( interface01, Slo4 of  BBU) also, pls repeat 5.3.2.1 steps.
Ps: sometime AAU can take two CPRI .
5.3.4SFP of AAU2 Checking
Move tested SFP to other good cell  link .pls repeat 5.3.2.1 steps.
Ps: sometime AAU can take two  SFP,pls do  switch  test one by one. Do not do two switch test  at same time , pls.
5.3.5CPRI of AAU  Checking
Move tested CPRI to other good cell  link .pls repeat 5.3.2.1 steps.
Ps: sometime AAU can take two  CPRI,pls do  switch  test one by one. Do not do two switch test  at same time , pls.
5.3.6the interface 01 of board UBBPg2a(  Slo5 of BBU) Checking
Move other good cell link to this  interface.pls repeat 5.3.2.1 steps.
5.3.7If there is link to the interface 01  of board UBBPg2a( Slo4 of BBU), pls do this Checking
Move other good cell link to this  interface.pls repeat 5.3.2.1 steps.
5.3.8AAU2(AAU5645) checking
Move other good cell link to AAU2 ,  pls repeat 5.3.2.1 steps.
5.3.9Confirmation
Certenly, when all parts have been  tested, we can move good part to broken AAU2 link for confirmation.
If you think it not necessary, this  step can be ignored.
6, Apply  spare
If manager ask, pls put all PIC in  sheet "PIC" in this test report,
If manager is nice people, just show  related PIC to him.
Write down SN code and hardware  type, send it to manager . Then spare will be prepared in a few days.
Work is done, thank you for efforts.

举报本楼

您需要登录后才可以回帖 登录 | 注册 |

版规|手机版|C114 ( 沪ICP备12002291号-1 )|联系我们 |网站地图  

GMT+8, 2025-8-21 17:33 , Processed in 0.254762 second(s), 17 queries , Gzip On.

Copyright © 1999-2025 C114 All Rights Reserved

Discuz Licensed

回顶部